Request for Proposals (RFP) for City of Chicago Municipal Electricity Supply, including Renewable Generation
On behalf of the City of Chicago (“City”), the Department of Assets, Information and Services (“AIS”) is seeking an Electricity Sales Agreement (“ESA”) with an electricity supplier to meet the City’s municipal electricity requirements and renewable electricity generation goals.
SCHEDULE:
RFP Schedule Description | Date* |
---|---|
RFP Issued | September 4, 2020 |
Pre-Proposal Webinar | September 10, 2020 |
Request for Clarification Deadline | September 21, 2020 |
City Responses to Requests for Clarification | October 6, 2020 |
Proposal Due Date | November 6, 2020 |
Respondent Interviews | Multiple Dates |
Selection of Selected Respondent | December 11, 2020 |
Contract Awarded | TBD |
*All RFP schedule descriptions and dates are tentative and subject to change. |
DOCUMENTS
- City of Chicago Request for Proposals RFP including Renewable Energy Generation 09042020
- City of Chicago Electricity Sales Agreement 09042020
- ADDENDUMS
- CLARIFICATION